Bridge delayed capacity

What threemonths latecosts you

Turn schedule slip into a decision model. Compare the cost of waiting with a site-specific bridge-capacity plan that runs alongside the delayed project.

Illustrative delay estimate
Delayed project capacity
Expected delay
MW × months

Formula: capacity band × delay band × $500,000 to $1.25 million per MW per month - a supplied handoff estimate pending substantiation. Illustrative delay economics only. Not Pacific pricing, not a quote.

Parallel
Site and factory work
One truck
Module arrival
Craned
Onto a prepared pad
Remote
Commissioning path
Method

Price the delay

The estimate uses bands and ranges, not false precision. Assumptions are shown with every result.

1. Capacity

Select the delayed capacity band in MW. No confidential site values are collected.

2. Schedule

Select the expected delay band in months.

3. Range

See the estimated owner cost range and the assumptions behind it: $500,000 to $1.25 million per MW per month, a supplied industry estimate pending substantiation.

Price your delay
Sequence

A bridge plan runs in parallel

Site work is limited to a pad and power feed and happens while the module is built and burned in at the factory. The target schedule is set by a site-specific plan - targeted, never guaranteed.

Site scope
Prepared pad + power feed
Factory
Build and burn-in off-site
Arrival
Complete on one truck
Placement
Craned onto the prepared pad
Commissioning
Remote sequence
Scale
Pod by pod
Proof

Pod 32 proof, not a schedule promise

The reference module carries its own evidence. The schedule stays a site-specific target.

Reference load

645 kW operating load for the Pod 32 module: 32 Supermicro HGX B300 nodes, 256 NVIDIA B300 GPUs.

Storage

983 TB raw NVMe per module

Fabric throughput

Configurable 3.2 or 6.4 Tbps per node

24 stages

Factory, site, and integration test program with witnessed evidence at gates F-1 through F-7.

Targeted

Operational within roughly three months of pre-payment as a design target, confirmed site by site.

Objections

Risk, interfaces, economics, exit

What is fixed?

Site facts - pad, power feed, interconnection - are separated from supplied model assumptions in every conversation.

What is movable?

Redeployment paths and contract terms for the bridge period are defined privately on the call.

What does it cost?

The delay estimate is not Pacific pricing. Commercial terms are discussed on a qualified call.

Book

From estimate to engineering call

Three quick questions - role, driver, timeline - then the calendar opens. No site addresses, project names, or financial exposure collected.

1 / 3

Your role

Bridge-capacity call

Answer the three questions and the calendar opens here. Prefer to skip ahead? Book directly on Cal.com.

FAQ

Method and schedule

How is the delay estimate calculated?

Capacity band times delay band times $500,000 to $1.25 million per MW per month - a supplied industry estimate pending substantiation. It models what a late site costs its owner in depreciation and lost lease. It is illustrative delay economics, never Pacific pricing or a quote.

How fast can bridge capacity be live?

Each module is targeted to be operational within roughly three months of pre-payment - a design target confirmed site by site, not a guarantee. Factory build and burn-in run in parallel with site preparation.

What site work is needed?

A prepared pad and a power feed. The module arrives complete on one truck, is craned onto the pad, and is commissioned remotely.

Can the capacity move later?

Modules arrive complete on one truck and are craned onto a prepared pad, so redeployment paths exist when the permanent site comes online. Exact redeployment and contract terms are defined privately.

Is the calculator a quote?

No. It estimates the cost of the delay itself from published assumptions and bands. Pacific commercial terms are discussed only on a qualified call.

Turn schedule risk into a decision

Price your delay